The project

Our role.

HVAC works for STT Data Centre Mumbai.

  • HVAC

Project overview

Facts and scope of work.

Client
STT GDC IndiaST Telemedia Global Data Centres
Location
MIDC Mahape, Navi Mumbai
Status
Completed
Value
₹30 crProject register billed value
Facility
28.4 MW campus11 acres, Tier III
Programme
1 yearGround and first floor package in 3 months

HVAC supply, installation, testing and commissioning for the ground and first floors: the chilled water low side from the building headers, precision cooling installation, air side distribution and ventilation, supports and insulation, and performance verification.

01

Fast track in a live facility

The ground and first floor package delivered in three months inside an operating data centre under the operator's methods of procedure, hot work permits and controlled shutdowns.

02

Precision

Temperature to ±1 °C and humidity to ±5% RH, with leak tested joints and validated containment around live IT equipment.

03

Acceptance

Testing to the operator's protocol with NABL calibrated instruments and witnessed records, to ASHRAE thermal guidelines and SMACNA duct standards.

Scope of work by service

Select a service

Chilled water distribution and CRAH, PAC, AHU and FCU connections. Valves, ductwork, insulation and air terminals. Ventilation for electrical, UPS and battery rooms, with precision cooling interfaces.

MEP totals 95%: HVAC 92% and Electrical 3%. ELV & BMS is 5%. The split illustrates scope; it does not measure contract value, quantities or progress.

Zero downtime on existing infrastructure through the programme, the first of three mission critical awards in Navi Mumbai.